Warranty & Pool-Care HandoverAvailable at completion
Pending
Draw Schedule & Invoices
Draw 1 — Design & EngineeringPaid Feb 20, 2026
$28,500Paid
Draw 2 — Excavation & SteelPaid Apr 8, 2026
$46,000Paid
Draw 3 — Gunite / ShotcreteDue upon shell completion
$52,000Due Now
Draw 4 — Tile, Coping & DeckingUpcoming
$61,000Upcoming
Draw 5 — Plaster & StartupFinal draw
$34,500Upcoming
Balance due now: $52,000
Payment initiated (demo). A receipt would be emailed and this draw marked Paid.
Project Budget
Contract totalSilverleaf estate pool
$222,000
Paid to dateDraws 1–2
$74,500
RemainingDraws 3–5
$147,500
Approved change orders1 (see Change Requests)
+$6,800
Allowances
Glass tileSelected within allowance
On budget
Decking / travertineUpgraded — see CO #1
+$6,800
Change Requests
CO #1 — Travertine deck upgradeApproved · +$6,800 · May 2
Approved
CR #2 — Add second fire bowlEstimate in review
In Review
CR #3 — Baja shelf umbrella sleeveRequested May 28
Submitted
Submit a Change Request
Messages — Project Team
JS
John SmieszekMay 30, 8:12a
Shell looks great after the shot — we're into the 28-day cure now. I'll walk the coping layout with you on the 14th. Renders for the second fire bowl are attached in Design.
RB
YouMay 30, 9:40a
Perfect, thank you! We love the twilight render. Go ahead and price the second fire bowl.
MC
Maria — Project CoordinatorJun 1, 11:05a
Draw 3 invoice is posted under Invoices & Draws. Tile arrives the week of the 9th; coping install starts the 12th.
JS
John SmieszekJun 2, 7:22a
Second fire-bowl estimate is in your Change Requests as CR #2. No work starts until you approve it.